Initiation

Initiation was initially carried out by David Smyth (production), Mark Lang (dev tech) and Franck Bergeret (project services) in Aug 2012. Initial meeting held to dicuss proposals, scope and objectives required for the project Brief.

Further meeting to review Brief was held with SACS (Karen Osterburg and Ruth McCallum)  and PM in September, as well as with Ruth, Iain Fiddes, Mark Lang and PM.

Project Info

Project
Retirement of EUCLID Web Servers
Code
SAC013
Programme
Student Systems Partnership SSP
Project Manager
Franck Bergeret
Project Sponsor
Karen Osterburg
Current Stage
Close
Status
Closed
Start Date
22-Aug-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
15-Mar-2013
Programme Priority
5
Overall Priority
Normal
Category
Compliance