Impact

 

Priority and Funding

 Project is Essential as the current Web Servers will stop being supported by Sun Oracle from July 2013. Funding 51 days, 12/13 Core funding.

Priority 2 (should this be delayed to after the SITS upgrade, priority would have to be reviewed).

 

Impact and Dependencies

 

This decommission must be completed before the SITS Double Upgrade is done (SAC011), which is due in Dev 3/12/2012, Test early 21/01/2013, and go Live date 22/02/2013. Testing for this project should not be run in parallel with testing the upgrade.

 

Business activities to consider when going live:

  • Graduation (end Nov/ December)
  • Assessment period (January)
  • Mini portfolios cut-off date (after 15th Jan).

 

Project Info

Project
Retirement of EUCLID Web Servers
Code
SAC013
Programme
Student Systems Partnership SSP
Project Manager
Franck Bergeret
Project Sponsor
Karen Osterburg
Current Stage
Close
Status
Closed
Start Date
22-Aug-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
15-Mar-2013
Programme Priority
5
Overall Priority
Normal
Category
Compliance