April 2014
- Report Date
- April 2014
Achievements in last period
- TRN (Training environment) upgrade signed off
- adressing annual roll over not working in SITS: writing it outside SITS, build progressing, solution to be completed in May, so that refresh of Test can be done
Issues
- none
Next Steps
- 2nd refresh of Test following roll over solution fix
- Close
15-May-2014 | Second Refresh of TEST from LIVE completed |
22-May-2014 | Deployment review 2 |
02-Jun-2014 | Close |
- Approved budget
- 230.0 days
- Activity this month
- 16.1 days
- Activity this year
- 211.7 days
- Activity to date
- 211.7 days
- Estimate to complete current year
- 17.9 days
- Estimate to complete future years
- 0.0 days