April 2014

Report Date
April 2014

Achievements in last period

  • TRN (Training environment) upgrade signed off 
  • adressing annual roll over not working in SITS: writing it outside SITS, build progressing, solution to be completed in May, so that refresh of Test can be done 

Issues

  • none

Next Steps

  • 2nd refresh of Test following roll over solution fix
  • Close

 

15-May-2014Second Refresh of TEST from LIVE completed
22-May-2014Deployment review 2
02-Jun-2014Close

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
230.0 days
Activity this month
16.1 days
Activity this year
211.7 days
Activity to date
211.7 days
Estimate to complete current year
17.9 days
Estimate to complete future years
0.0 days

Project Info

Project
SITS Upgrade
Code
SAC024
Programme
Student Systems Partnership SSP
Project Manager
Franck Bergeret
Project Sponsor
Karen Osterburg
Current Stage
Close
Status
Closed
Start Date
20-Aug-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
11-Jul-2014
Programme Priority
2
Overall Priority
Normal
Category
Compliance