Report for May 2014

Report Date
May 2014

Achievements in Last Period

  • Project Brief Sign-Off
  • Requirements documented and signed off
  • Decision made for the project to be developed within Student Systems not go to Tribal.
  • SITS development Started

Issues

  • n/a

Next Steps   

  • Complete SITS development
  • Complete BOXI Development
  • Acceptance Testing
  • Arrange Handover
  • Go Live Start of July.

 

13-Jun-2014SITS Development Complete
23-Jun-2014Reporting Development Complete
09-Jul-2014Testing Complete
11-Jul-2014Go Live
31-Jul-2014Close

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
25.0 days
Activity this month
0.4 days
Activity this year
1.5 days
Activity to date
1.5 days
Estimate to complete current year
24.1 days
Estimate to complete future years
0.0 days

Project Info

Project
PGR Engagement Monitoring
Code
SAC032
Programme
Student Systems Partnership SSP
Project Manager
Ruth McCallum
Project Sponsor
David Williams
Current Stage
Close
Status
Closed
Start Date
07-Apr-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
01-Aug-2014
Category
Compliance

Documentation