Report for May 2014
- Report Date
- May 2014
Achievements in Last Period
- Project Brief Sign-Off
- Requirements documented and signed off
- Decision made for the project to be developed within Student Systems not go to Tribal.
- SITS development Started
Issues
- n/a
Next Steps
- Complete SITS development
- Complete BOXI Development
- Acceptance Testing
- Arrange Handover
- Go Live Start of July.
13-Jun-2014 | SITS Development Complete |
23-Jun-2014 | Reporting Development Complete |
09-Jul-2014 | Testing Complete |
11-Jul-2014 | Go Live |
31-Jul-2014 | Close |
- Approved budget
- 25.0 days
- Activity this month
- 0.4 days
- Activity this year
- 1.5 days
- Activity to date
- 1.5 days
- Estimate to complete current year
- 24.1 days
- Estimate to complete future years
- 0.0 days