Project Status Reports

Title Report Date Time Cost Scope Overall Change
February 2017 February 2017 GREEN GREEN GREEN GREEN
January 2017 January 2017 GREEN GREEN GREEN GREEN
November 2016 November 2016 AMBER AMBER GREEN AMBER
October 2016 October 2016 AMBER AMBER GREEN AMBER
September 2016 September 2016 GREEN AMBER AMBER AMBER
August 2016 August 2016 GREEN AMBER AMBER AMBER
July 2016 July 2016 GREEN AMBER GREEN AMBER
June 2016 June 2016 GREEN GREEN GREEN GREEN
May 2016 May 2016 GREEN GREEN GREEN GREEN
End of April 2016 April 2016 AMBER GREEN GREEN AMBER
End of March 2016 March 2016 RED GREEN RED RED
End of February 2016 February 2016 GREEN GREEN GREEN GREEN
January 2016 January 2016 GREEN GREEN GREEN GREEN
November 2015 November 2015 GREEN
October 2015 October 2015 GREEN GREEN

Project Info

Project
Use of Student Data: Dashboards
Code
SAC044
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Jamie Morton
Project Sponsor
Barry Neilson
Current Stage
Close
Status
Closed
Start Date
13-Aug-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
14-Apr-2017
Programme Priority
2
Overall Priority
Normal
Category
Discretionary