Organisation

Work/Task Breakdown and Project Governance

Task

Deliverable

Owner

Project Management

Project authorisation, Planning and Project documents. Communication and coordination with stakeholders. 

Manage project, sign off, resources, budget and reporting.

Project Services

Build It

Review refresh procedure

Refresh DEV, TEST, TRN environments 

Manage software update

Scripts and refresh tasks

SSP BA

IS Dev Tech

IS Apps Man, SSP BA

SSP IS

Test Refresh DEV

SSP IS

Test Refresh TEST and TRN environments

SSP BA, SS Operations

Analyse Upgrade, User Stories

SSP BA

Review upgrade procedure

Upgrade DEV Scripts

SSP BA, Project Services

IS Dev Tech/ SSP IS

Manage software updates, Configuration changes

IS Apps Man, Dev Tech, SSP IS

Check DEV Upgrade

SSP IS

  Automate performence testing scrips for LIVE SSP IS, IS Apps Man

Check It

Upgrade TEST -Scripts

IS Dev Tech, SSP IS, SSP

Manage software updates, configuration changes

IS Apps Man , Dev Tech, SSP IS

Check TEST upgrade- Manage SITS and downstream system communication

SSP BA

ASOR

Dev Tech, IS Apps Man, SSP BA,

SSP IS

Document & handover

Implementation plan

IS Dev Tech, IS Apps Man and SSP IS/BA

Update existing TAD and review

IS Dev Tech, IS Tech Man

  Communications to LIVE users SSP Operations

Deploy

Upgrade LIVE- Scripts

Dev Tech/SSP IS

Manage software updates,  configuration changes

IS Apps Man, Dev Tech

Test LIVE Upgrade

Manage SITS and downstream system communication

SSP BA

 

Upgrade DUST  

Dev Tech/SSP IS

Refresh TEST from LIVE

DevTech, SSP IS

Close It

Closure Review

Project Services, Dev Tech, SSP IS/BA, IS Apps Man, Student Systems operations

 

Resources Skills and Cost

SSP IS Apps Estimate = 210 days, to be re-estimated after upgrade of DEv environment.

SSP Registry Estimate =120  days (for impact analysis and regression testing for the upgrade )

 

Project Milestones

18-Nov-2016

End of Planning

28-Nov-2016

Complete refreshes of DUST, DEV, TEST

05-Dec-2016

Upgrade DEV

05-Dec-2016

Deliver automated performance testing in LIVE

16-Dec-2016

Sign off DEV upgrade

19-Dec-2016

Refresh TRN

09-Jan-2017

Upgrade TEST

03-Feb-2017

Sign off TEST upgrade

06-Feb-2017

Upgrade TRN

25-Feb-2017

Upgrade LIVE

18-Mar-2017

Fallback date LIVE upgrade

24-Mar-2017

Deployment Sign off

03-Apr-2017

Refresh TEST from LIVE

10-Apr-2017

Upgrade DUST

21-Apr-2017

Close