Report for February 2017
- Report Date
- February 2017
Achievements this period
- Sign off TEST upgrade
- TRN upgraded
- Project re-estimated with small contingency remaining
Issues
- Several JIRA issues remain but none are "must-haves" and are not likely to prevent the LIVE upgrade from proceeding
- The file-locking issue, identified as a risk to the LIVE upgrade, does not yet have a proven solution, although a research-services resource may be available to assist over the upgrade weekend.
Next Steps
- TRN upgrade, including test of measure to alleviate file-locking issue in LIVE
- Sign off TRN
- LIVE upgrade
Milestones
17-Mar-2017 | Upgrade LIVE | ||
01-Apr-2017 | Fallback date LIVE upgrade | ||
14-Apr-2017 | Deployment Sign off | ||
25-Apr-2017 | Refresh TEST from LIVE | ||
02-May-2017 | Upgrade DUST | ||
19-May-2017 | Close |
- Approved budget
- 210.0 days
- Activity this month
- 39.0 days
- Activity this year
- 147.0 days
- Activity to date
- 147.0 days
- Estimate to complete current year
- 64.0 days
- Estimate to complete future years
- 0.0 days