Report for March 2017

Report Date
March 2017

 

Achievements this period

 

  • Sign off TRN upgrade
  • LIVE upgrade delivered
  • Project budget increased by 20 days to replace contingency

Issues

 

  • Several JIRA issues remain to be resolved

 

Next Steps

 

  • Sign off LIVE upgrade
  • Refresh TEST from LIVE
  • Clone DUST from TEST

 

Milestones

 

14-Apr-2017     Deployment Sign off
25-Apr-2017     Refresh TEST from LIVE
02-May-2017     Upgrade DUST
19-May-2017     Close

 

 

Project Status
RAG Status
Time
GREEN
Cost
AMBER
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
230.0 days
Activity this month
29.0 days
Activity this year
176.0 days
Activity to date
176.0 days
Estimate to complete current year
54.0 days
Estimate to complete future years
0.0 days