Report for March 2017
- Report Date
- March 2017
Achievements this period
- Sign off TRN upgrade
- LIVE upgrade delivered
- Project budget increased by 20 days to replace contingency
Issues
- Several JIRA issues remain to be resolved
Next Steps
- Sign off LIVE upgrade
- Refresh TEST from LIVE
- Clone DUST from TEST
Milestones
14-Apr-2017 | Deployment Sign off | ||
25-Apr-2017 | Refresh TEST from LIVE | ||
02-May-2017 | Upgrade DUST | ||
19-May-2017 | Close |
- Approved budget
- 230.0 days
- Activity this month
- 29.0 days
- Activity this year
- 176.0 days
- Activity to date
- 176.0 days
- Estimate to complete current year
- 54.0 days
- Estimate to complete future years
- 0.0 days