Report for April 2017

Report Date
April 2017

 

Achievements this period

 

  • LIVE upgrade signed off
  • TEST environment refreshed and signed off
  • Handover of performance tests completed.

Issues

 

  • Several JIRA issues remain to be resolved. These are mainly with the vendor and are not expected to delay closure.
  • A change of scope (to cope with  client crashes more frequent since the upgrade) must be approved

 

Next Steps

 

  • Clone DUST from TEST
  • Close

 

Milestones

 

02-May-2017     Upgrade DUST
19-May-2017     Close

 

 

Project Status
RAG Status
Time
GREEN
Cost
AMBER
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
230.0 days
Activity this month
29.0 days
Activity this year
176.0 days
Activity to date
176.0 days
Estimate to complete current year
54.0 days
Estimate to complete future years
0.0 days