Report for April 2017
- Report Date
- April 2017
Achievements this period
- LIVE upgrade signed off
- TEST environment refreshed and signed off
- Handover of performance tests completed.
Issues
- Several JIRA issues remain to be resolved. These are mainly with the vendor and are not expected to delay closure.
- A change of scope (to cope with client crashes more frequent since the upgrade) must be approved
Next Steps
- Clone DUST from TEST
- Close
Milestones
02-May-2017 | Upgrade DUST | ||
19-May-2017 | Close |
- Approved budget
- 230.0 days
- Activity this month
- 29.0 days
- Activity this year
- 176.0 days
- Activity to date
- 176.0 days
- Estimate to complete current year
- 54.0 days
- Estimate to complete future years
- 0.0 days