Report for August 2017

Report Date
August 2017
Achievements in this reporting period:
  • I9 - PPMD frontend decommissioned
  • Project  closed

Resolved issues:

 

Open issues:

 

Next Steps:

Project Status
RAG Status
Overall
BLUE
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Continuous Improvements
Code
SAC059
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Karen Osterburg
Project Sponsor
Barry Neilson
Current Stage
Close
Status
Closed
Start Date
01-Aug-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
16-Aug-2017
Overall Priority
Normal
Category
Discretionary