Report for February 2018

Report Date
February 2018

Achievements in the Last Period

  • The APT Board meeting took place on 14 February. The revised version of the project brief, new estimate and plan were well received and have been signed off. They were also approved by ISG governance and QA Board on 16 February 2018, see End of Planning milestone. Resources booked and Go CAB Change Requests for Phase 1 release have been booked according to the plan.

  • Sprint 3 took place between 7-21 February but no release was produced because no Jira was completed. The milestone for Sprint 3 release was withdrawn.

  • Sprint 4 started on 21 Feb with aim to produce a release on 7 March. Several Jiras have already been fixed as the development velocity is increasing due to the second developer on the project. However, because of the Change Freeze on IS system from 23 Feb to 21 Mar due to industrial action releases have had to be rescheduled. This will not change the end of Phase 1 (Delivery - End of Development Phase 1 (Sprint 1-6)) scheduled for 14 May 2018.

    • Sprint 4 will now last for 4 weeks and end on 21 Mar 2018.

    • Sprint 5 will start on 21 Mar and end on 4 Apr 2018.

    • Sprint 6 will end as  planned on 14 May 2018.

  • Documentation, training and support work is ongoing.

Issues

Next Steps

  • Secure new staff allocation
  • Development Sprint 4 and release

 

Project Status
RAG Status
Time
GREEN
Cost
RED
Scope
GREEN
Overall
RED
RAG Commentary
Change - The revised budget, plan and timeline have been approved. Not an issue, no input from ISG SMT needed.
Change Status
Activity
Approved budget
402.0 days
Activity this month
29.1 days
Activity this year
74.5 days
Activity to date
74.5 days
Estimate to complete current year
165.5 days
Estimate to complete future years
162.0 days

Project Info

Project
Assessment and Progression 3
Code
SAC063
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Franck Bergeret
Project Sponsor
Susan Rhind
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
21-Aug-2017
Planning Date
26-Jan-2018
Delivery Date
31-Jul-2018
Close Date
30-Aug-2019
Overall Priority
Normal
Category
Discretionary