Report for June 2018
- Report Date
- June 2018
Report by Morna Findlay for June 2018
Achievements this month
- Additional testing and backout steps for Deletions 1 (Part 2)
- New delivery date for Deletions 1 agreed with Business
- Part 2 of Deletions 1 approved by CAB
- Deletions 2 (uncompleted applications) in testing
Issues
- Delay in final BI delivery step much be completed before 25/7/18
- Emerging conflict for the BA resource with SAC063 (APT3) - PM investigating
- Emerging issue which may cause plans to delete UUNs from reporting universes to be reviewed
Next Steps
- Deliver Deletions 1 and Deletions 2
- Complete analysis to inform size and scope of follow-on project
Milestones
- Approved budget
- 130.0 days
- Activity this month
- 11.0 days
- Activity this year
- 71.0 days
- Activity to date
- 75.0 days
- Estimate to complete current year
- 35.0 days
- Estimate to complete future years
- 0.0 days