Report for August 2018
- Report Date
- August 2018
Report by Morna Findlay for August 2018
Achievements this month
- Deletions 2 (uncompleted applications) deployed in TRN and LIVE
- Changes to online registration forms deployed in TRN and LIVE
- Addition of new objects into MI universes deployed in TRN and LIVE
- Decision not to remove UUNs from MI universes as part of this project approved by senior management
- Change to project budget approved
- Change to project scope and Closure milestone agreed with project sponsor
Issues
- Conflict for the BA resources with SAC063 (APT3) continues - to be resolved with Programme owner - closure to be delayed
Next Steps
- Approve change to project scope and milestones
- Complete analysis to inform size and scope of follow-on project
- Complete EqIA and DPIA
- Close
Milestones
- Approved budget
- 110.0 days
- Activity this month
- 9.0 days
- Activity this year
- 9.0 days
- Activity to date
- 94.0 days
- Estimate to complete current year
- 10.0 days
- Estimate to complete future years
- 0.0 days