This is the project which seeks to implement the student funding processes (delivered by SAC046)in all schools.

Current project status

Report Date RAG Budget Effort Completed Effort to complete
November 2019 BLUE 0.0 days 0.0 days 0.0

Project Info

Project
Student Funding 2 (Implementation)
Code
SAC070
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Andrew Mackenzie
Project Sponsor
Tracey Slaven
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
01-Mar-2018
Planning Date
n/a
Delivery Date
19-Aug-2019
Close Date
09-Sep-2019
Programme Priority
3
Overall Priority
Normal
Category
Discretionary

Documentation

Project Dashboard

Project journal

No entries found.

Change dashboard

Nothing to report.