Staff in  colleges and schools regularly raise the issue  that performance of UG/PG Admissions is unsatisfactory during the peak period (Jan – March).  The performance problems measurably impact on their ability to process applications to the stated deadlines with their budgeted resources.  The business objectives cannot currently be fulfilled without overtime, goodwill and luck.

 

This project will to look at a way to reduce the response time for the most used area (switching tabs within the same applicant) in UG.  It will also gather evidence enabling the team to direct development efforts in those areas most likely to have a significant performance improvement visible to users before the peak period begins in January 2019. 

 

The evidence gathered may be used to make further improvements in a follow-on project.

Current project status

Report Date RAG Budget Effort Completed Effort to complete
October 2019 BLUE 199.0 days 201.0 days 0.0

Project Info

Project
EUCLID Performance Improvements
Code
SAC075
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Chris Konczak
Project Sponsor
Lorna Halliday
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
01-Oct-2018
Planning Date
07-Dec-2018
Delivery Date
20-Mar-2019
Close Date
19-Jun-2019
Programme Priority
1
Overall Priority
Normal
Category
Discretionary