October 2023

Report Date
October 2023

Achievements in Last Period

5 releases to Live: 

  • Live issue-Predicted grades not fully displaying in EUCLID/UG admissions
  • WP Contextual Admission checker : 2 enhancements following change done at cycle change over
  • ESC  enhancement to wording changes and web links
  • Google analytics: old code removed for PATH and WP checker

Issues

  • There is a backlog of stories to get signed off in TRN, this is the impact of BAU priorities from student systems operations

Next Steps

  • Deploy remaining changes: (1)remove old Google analytics code across Euclid applications (2) Letter of Completed Studies extended to cover Nov 2023 Graduations (3)Move to Student HESA Id to report statutory return (4)Looping search in Direct Admissions-bug
  • ESC- dashboard usability analysis - meeting planned with users- will inform training , functionality change
  • Close project 

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
100.0 days
Activity this month
149.0 days
Activity this year
149.0 days
Activity to date
1689.0 days
Estimate to complete current year
7.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Student Record Enhancement
Code
SAC084
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Franck Bergeret
Project Sponsor
Lizzie Beattie
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
17-Aug-2020
Planning Date
14-Aug-2020
Delivery Date
31-Aug-2023
Close Date
15-Dec-2023
Programme Priority
3
Overall Priority
Normal
Category