November 2023

Report Date
November 2023

Achievements in Last Period

4 releases to Live: 

  • XML link upgrade enhancement: the 2023 cycle Applicant records are populated so that we can import the end of cycle HESA data
  • Direct Admissions looping bug fixed, improving user experience
  • Legacy code: remove old Google Analytics tagging from EUCLID code and DRPS
  • Hide 'Current location & engagement method for COVID-19 response' from Student Hub

Issues

  • closure report shared but not signed off by all due to other business priorities with the graduation taking place

Next Steps

  • Deploy remaining changes: (1)Move to Student HESA Id to report statutory return 
  • ESC- dashboard usability analysis -to inform training , functionality change
  • Close project 
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
BLUE
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
100.0 days
Activity this month
38.0 days
Activity this year
187.0 days
Activity to date
1728.0 days
Estimate to complete current year
10.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Student Record Enhancement
Code
SAC084
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Franck Bergeret
Project Sponsor
Lizzie Beattie
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
17-Aug-2020
Planning Date
14-Aug-2020
Delivery Date
31-Aug-2023
Close Date
15-Dec-2023
Programme Priority
3
Overall Priority
Normal
Category
Discretionary