February 2023
- Report Date
- February 2023
Achievements in Last Period
-
Objective 1: Deletion for APT low level components: hypothesis done on performance testing, drafted option paper , but no progress with consultation
- Objective 2: Deletion of unsuccessful applicants- signed off the retention period from the earlier engagement held with Admissions, GaSP and colleges, but not the DPIA (data protection impact assessment)
-
Objective 3: Deletion of meta data: completed: deployed to Live and handed over as business as usual - But not the unsubmitted applicants
Issues
- Decision made by SSP management to suspend this project once all documentation of work in progress has been done: The decision was made as a result
- Impact on conflicted resources- BA and developers are required to move to prioprity projects: Student Support and ESC which have hard deadlines this summer
- Impact of strike on consultation required for the 1st objective/deletion for APT low level components
- Objective 2 technical solution has raised an issue that requires an impact assessment before build can progress - Articulate solution and then suspend till new developers are available
Next Steps
- Progress with technical solution analysis and then suspend
- Progress with deploying unsubmitting applications deletion
- Progress with APT deletion options and then suspend
Milestones
Deliver | Deletion of annual progression records of students' low level of assessments/individual marks at assessment question level before next Jan Board | 30-Jan-2023 |
Plan | Review next priorities- Will inform next milestones | 10-Feb-2023 |
Deliver | Apply clean up strategy for unused data (meta data and unsubmitted applications) | 13-Feb-2023 |
Deliver | Deletion of unsuccessful applicants | 03-Apr-2023 |
Close | Closure |
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days