Achievements in Last Period

  • Objective 1: Deletion for APT low level components: hypothesis done on performance testing, drafted option paper , but no progress with consultation

  • Objective 2: Deletion of unsuccessful applicants- signed off the retention period  from the earlier engagement held with Admissions, GaSP and colleges, but not the DPIA (data protection impact assessment)
  • Objective 3: Deletion of meta data: completed: deployed to Live and handed over as business as usual - But not the unsubmitted applicants

     

Issues

  • Decision made by SSP management to suspend this project once all documentation of work in progress has been done:  The decision was made as a result 
    • Impact on conflicted resources- BA and developers are required to move to prioprity projects: Student Support and ESC which have hard deadlines this summer  
    • Impact of strike on consultation required for the 1st objective/deletion for APT low level components
  • Objective 2 technical solution has raised an issue that requires an impact assessment before build can progress - Articulate solution and  then suspend till new developers are available

Next Steps

  • Progress with technical solution analysis and then suspend
  • Progress with deploying unsubmitting applications deletion
  • Progress with APT deletion options and then suspend

Milestones

Deliver Deletion of annual progression records of students' low level of assessments/individual marks at assessment question level before next Jan Board 30-Jan-2023
Plan Review next priorities- Will inform next milestones 10-Feb-2023
Deliver Apply clean up strategy for unused data (meta data and unsubmitted applications) 13-Feb-2023
Deliver Deletion of unsuccessful applicants 03-Apr-2023
Close Closure
Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
GREEN
Overall
AMBER
RAG Commentary
Amber as a result of SSP resources conflicted for higher priority work (ESC enhancements and Student Support), the project will need to be suspended until new resources are recruited . Impact: programme risk accepted
Change Status
Has formal escalation taken place?
Yes
Escalated to
project sponsor
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
GDPR 2 for student systems
Code
SAC085
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Franck Bergeret
Project Sponsor
Lizzie Beattie
Current Stage
Build
Status
Withdrawn
Project Classification
Run
Start Date
01-Oct-2021
Planning Date
29-Oct-2021
Delivery Date
03-Apr-2023
Close Date
30-Jun-2023
Programme Priority
4
Overall Priority
Normal
Category
Compliance