This project is to take the SITS Hub/Streams off the physical servers.

This is done as a separate project 1st, as Streams (the Oracle tool that replicate data from primary database to downstreams database) is reaching end of life next year and is causing operational reporting issues. This is to be followed by another project for moving the database to VM (after the next SITS upgrade due Nov 2021, due to its dependency).

This is to prepare for the end of life of the physical servers due in  March 2022

 

Current project status

Report Date RAG Budget Effort Completed Effort to complete
April 2021 GREEN 0.0 days 0.0 days 0.0

Project Info

Project
Move the SITS Hub/Streams off the physical servers to VM
Code
SAC086
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Anne Mathison
Project Sponsor
Brandi Headon
Current Stage
Build
Status
In Progress
Project Classification
Run
Start Date
27-Jul-2020
Planning Date
20-Aug-2020
Delivery Date
30-Jul-2021
Close Date
15-Sep-2021
Overall Priority
Highest
Category
Compliance