Organisation

Work/Task Breakdown

  • New developers staff training 

  • System analysis, review current change-based events 

  • Review downstream systems' requirements: work with CAM and Timetabling project teams to understand their requirements 

  • Design API, workflow, error handling, end points 

  • Work with IS Apps to ensure the integration with tools such as WSO2 and the architecture fit with the University integration plans, naming dictionary Federated University Data Mode

  • Build API, Peer Review 

  • Open access TEST Euclid (Live and Dev sorted during CMS work) 

  • Function testing API 

  • Test cases with CAM and Timetabling users- use a sandbox to show data are passed to users’ end points 

  • Documentation, review Data Access Protocol 

  • Deploy API 

  • Review integration with downstream users  

  • Review benefits realisation 

 

Resources, Skills and Costs

The resources for this project come from within Core SSP team, based on 2 SSP developers for the duration of the project: 

SSP Dev = 195 days - Used so far end July:  45 days (incl training new developers), plus Aug-Jan: 5 months & 15 days/month * 2= 150 days 

PM 10 days  

IS Apps small: EA for consultation only , and Production for releases, Dev Tech to open access of Test environments = 5 days 

Total IS budget= 210 days 

Additional resources not accounted in budget above: 

  • Student Systems reporting manager 

  • Student Systems Operations 

  • SSP tester 

 

Project Governance

 

  • Project governance by SSP management team (weekly meeting: sponsor, PM, SSP team leaders) 

  • Monthly reporting and meeting for non-project team stakeholders- linked to the SSP management group meeting every 3 weeks 

  • Technical governance for opening access/firewall of Euclid Test environments 

Project Stakeholders

Name Business Area Role Communication Plan
Aaron McHale CAM senior user

consult

Balasri Gunasekaran (project team) SSP Dev Developer

stand up 

Chris Giles SSP BA lead SSP BA lead

Weekly governance 

Craig Warrack Student records Operations manager, Student Systems Student records Operations manager

inform

David Ferreira (project team) SSP developer Lead developer

stand up 

Defeng Ma SSP Dev SSP dev team leader

stand up 

Weekly governance 

Franck Bergeret (project team) SSP programme manager Project Manager

stand up 

Weekly governance 

Jamie Morton SAIM student systems Reporting manager, data protection lead

consult

Jamie Thin IS Apps Timetabling programme manager  
John Allison IS apps Dev Services IS Apps Dev Services

Consult

Lizzie Beattie Head of Student Record Operations Project Sponsor

Weekly governance 

Luke Manley SSP SSP tester

consult

Marianne Brown, Scott Rosie Timetabling senior user

inform

Mark Lang Dev Tech IS Support

inform

Martin Jones Enterprise Architecture, IS Apps Integration architect

inform

Natalia Oleynik  (project team) SSP Dev Developer

stand up 

Seetha Subramanian IS Apps Application Management IS Support

inform

Stefan Kaempf IS Apps director Senior supplier

inform

Wilbert Kraan Data Architect Enterprise Architecture

 

Project Estimations

see above, SSP estimations based on effort over project duration, incl new developer training, support from senior Dev 

 

Project Info

Project
Delivering Student Records API
Code
SAC106
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Franck Bergeret
Project Sponsor
Lizzie Beattie
Current Stage
Build
Status
In Progress
Project Classification
Grow
Start Date
10-Jun-2024
Planning Date
28-Aug-2024
Delivery Date
27-Jan-2025
Close Date
28-Feb-2025
Overall Priority
Normal
Category
Discretionary

Documentation

Plan