September 2024

Report Date
September 2024

Achievements in Last Period

  • Completed design, workflow
  • Started build

Issues 

  • (on going) conflict approved for lead developer from P&M/enhancement to student creation, and for WS02 Choreo migration in Sep: managed conflict  but noted the impact is a delay in writing the design documentation for this project

Next Steps​

  • Continue system analysis/build
  • Review requirements from CAM
  • Mapping of the timetabling  integration to move from EUGEX to SITS
Build Build API 1st set: course and programme 07-Oct-2024
Build Build API 2nd set: Students 28-Oct-2024
Integrate Testing API 25-Nov-2024
Accept Test case with CAM 02-Dec-2024
Accept Test case with Timetabling 16-Dec-2024
Accept Rework API 15-Jan-2025
Deliver Deploy API 31-Jan-2025
Deliver Review DSOR 14-Feb-2025
Close Close 28-Feb-2025
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Delivering Student Records API
Code
SAC106
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Franck Bergeret
Project Sponsor
Lizzie Beattie
Current Stage
Build
Status
In Progress
Project Classification
Grow
Start Date
10-Jun-2024
Planning Date
28-Aug-2024
Delivery Date
27-Jan-2025
Close Date
28-Feb-2025
Overall Priority
Normal
Category
Discretionary

Documentation