September 2024
- Report Date
- September 2024
Achievements in Last Period
- Completed design, workflow
- Started build
Issues
- (on going) conflict approved for lead developer from P&M/enhancement to student creation, and for WS02 Choreo migration in Sep: managed conflict but noted the impact is a delay in writing the design documentation for this project
Next Steps
- Continue system analysis/build
- Review requirements from CAM
- Mapping of the timetabling integration to move from EUGEX to SITS
Build | Build API 1st set: course and programme | 07-Oct-2024 |
Build | Build API 2nd set: Students | 28-Oct-2024 |
Integrate | Testing API | 25-Nov-2024 |
Accept | Test case with CAM | 02-Dec-2024 |
Accept | Test case with Timetabling | 16-Dec-2024 |
Accept | Rework API | 15-Jan-2025 |
Deliver | Deploy API | 31-Jan-2025 |
Deliver | Review DSOR | 14-Feb-2025 |
Close | Close | 28-Feb-2025 |
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days