October 2024

Report Date
October 2024

Achievements in Last Period

  • Completed build API and PoC for CAM, demo work
  • Mapping of the timetabling  integration to move from EUGEX to SITS

Issues 

  • (new)  some delay to the milestones, not significant- Related to conflict from senior developer to support the project team

Next Steps​

  • Test API for CAM
  • Review requirements from TTU
  • Build API for TTU
Integrate Testing API for CAM changes 25-Nov-2024
Build Build API 2nd set: Students 29-Nov-2024
Accept Test case with CAM 02-Dec-2024
Integrate Testing API for TTU changes 16-Dec-2024
Accept Test case with Timetabling 17-Jan-2025
Accept Rework API 27-Jan-2025
Deliver Deploy API 31-Jan-2025
Deliver Review DSOR 14-Feb-2025
Close Close 28-Feb-2025
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Delivering Student Records API
Code
SAC106
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Franck Bergeret
Project Sponsor
Lizzie Beattie
Current Stage
Build
Status
In Progress
Project Classification
Grow
Start Date
10-Jun-2024
Planning Date
28-Aug-2024
Delivery Date
27-Jan-2025
Close Date
28-Feb-2025
Overall Priority
Normal
Category
Discretionary

Documentation