Current project status Report Date RAG Budget Effort Completed Effort to complete April 2025 AMBER 3,110.5 days 273.3 days 2650.9 Content Status In Progress Current Stage Execute Start Date Friday, 1 November 2024 Planning Date Tuesday, 25 March 2025 Delivery Date Friday, 12 December 2025 Close Date Friday, 27 November 2026 Project information Project Code SAC109 Programme Student Systems Partnership SSP Session 25/26 24/25 Organisational Unit Application Development and Operations Project Management Office (if relevant) ISG PMO Responsibility Applications Development and Operations Project Category Discretionary Project Classification Grow Project Type Implementation Project Size Large Project Complexity Simple Funding Source Core Funded Overall Priority Normal Student Impact Project deliverables will be used by students