Completion Report
Project Summary:
Background
Were the project goals met?
Were the project deliverables fully or partially accomplished?
The goals of the projects were:
The following deliverables were achieved (from project brief)
The following deliverables were not described in the Brief but were delivered:
Not Delivered:
Did the project deliver a solution to the problems being addressed?
What are the benefits for the business? How did it impact the business?
Does the Project Sponsor agree that this project can be closed at this time?
Cost Summary | ||||||||||||||
|
Analysis of Resource Usage:
Staff Usage Estimate: 1 days
Staff Usage Actual: 1 days
Staff Usage Variance: 0%
Other Resource Estimate: 1 days
Other Resource Actual: 1 days
Other Resource Variance: 0%
Explanation for variance:
- Budget
- Delivery date
Key Learning Points:
For projects involving both SSP IS and Other IS Apps resources, note which lessons are specifically for SSP and which are for IS Apps generally.
- What went well?
- What didn’t go so well?
- If you had a project like this again, what would you improve?
Outstanding issues:
List issues not solved, jira ref, and how/when they will be addressed