This project will create a single expert service, which will bring together institutional compliance and audit activity, operational compliance activity, and immigration advice and guidance for students.
Benefits
- Moving to a single team will improve service for students and colleagues in Schools and Colleges and introduce standardised processes.
- Clarified roles and responsibilities supporting compliance work.
This project will deliver the Target Operating Model being articulated in the Blueprint, approved by SA&S Board, in March 2018.
The details of the implementation are articulated in a Full Business Case, approved by SA&S Board too.
Plan
Project will be divided into below Workstreams (WS) to track the progress; identify, assign & complete various project actions; and for reporting purposes.
- WS1 – HR & People Transition
- WS2 – Change
- WS3 – Communications
- WS4 – Ways of Working
- WS5 – Logistics
- WS6 - Governance & Policy
Current project status
Report Date | RAG | Budget | Effort Completed | Effort to complete |
---|---|---|---|---|
November 2018 | GREEN | 0.0 days | 0.0 days | 0.0 |