Period Ending 21-Jan-19

Report Date
January 2019

Achievement in last period

  1. Closure report approved
  2. Project closed

Issues

None requiring escalated.

Risks

None - all risks now closed

Next Steps

  1. None

Milestones

 

Target Datesort descending Title Complete
30-Mar-2018 Planning Completed (D1.03) Yes
30-Mar-2018 Procurement Strategy Finalised and Approved (D4.03) Yes
02-Apr-2018 Communications Strategy Approved - Aligned to SAS Programme (D3.01) Yes
27-Jun-2018 Requirements, Cost Scoring and Weighting Finalised (D5.07) Yes
06-Jul-2018 Invitation to Tender (ITT) Published (D5.08) Yes
10-Aug-2018 Invitation to Tender (ITT) Notice Period Expires (D5.09) Yes
14-Sep-2018 Scoring Validated - Consensus Meeting (D6.05) Yes
28-Sep-2018 ITT Evaluation Period Ends (D6.08) Yes
07-Dec-2018 Contract Award Letters Issued (D7.06) Yes
07-Dec-2018 Contract Signed (D7.07) Yes
07-Dec-2018 Project Handover to Implementation Project (SAS013) (D8.01) Yes
10-Dec-2018 Contract Start Date (D7.09) Yes
17-Dec-2018 Project Closure (D8.02) Yes
Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
RAG Commentary
Project closed
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Change Commentary
Project closed.
Activity
Approved budget
98.0 days
Activity this month
1.0 day
Activity this year
35.0 days
Activity to date
132.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Work and Study Away - Procurement
Code
SAS012
Programme
Service Excellence - Student Administration and Support (SAS)
Management Office
Service Excellence PMO
Project Manager
Ranald Swanson
Project Sponsor
Chris Yeomans
Current Stage
Close
Status
Closed
Start Date
13-Mar-2018
Planning Date
07-Apr-2018
Delivery Date
07-Dec-2018
Close Date
21-Jan-2019
Overall Priority
Normal
Category
Discretionary

Documentation