As the EDW HR enhancement project has been completed, the ETL application (Talend project) is required to upgrade to the Talend Studio V8 as version 7 will not be supported after Nov 2024. In this upgrade needed to create and upgrade V8 branch for required projects, and in each of the Orchestration jobs that use the DBFiles the password encryption should be changed as the AES encryption method is no longer supported in V8. Then will Publish each of the projects to the TMC, run in DEV and TEST, and then when fully tested move to LIVE.  Also, some minor checks and improvements are required in some parts of the ETL infrastructure.

Current project status

Report Date RAG Budget Effort Completed Effort to complete
December 2024 GREEN 80.0 days 79.4 days 8.6

Project Info

Project
Talend Studio Application Upgrade
Code
SBI002
Programme
Strategic Business Intelligence (SBI)
Management Office
ISG PMO
Project Manager
Sepideh Samani Pour
Project Sponsor
Dave Berry
Current Stage
Execute
Status
In Progress
Start Date
04-Sep-2023
Planning Date
10-Oct-2023
Delivery Date
20-Jan-2025
Close Date
31-Jan-2025
Overall Priority
Normal

Documentation

Project Dashboard

Project journal

No entries found.

Change dashboard

Nothing to report.