Report for December 2015
- Report Date
- December 2015
Achievements in Last Period
- Technical evaluation workshops held
- Consultations with stakeholders begun
- Milestones reconfirmed by project manager, sponsor and team
Issues
- Several stakeholders remain to be contacted by the development leads
- Technical evaluation phase not to be completed before January, but broad direction is understood
Next Steps
- Complete technical evaluation phase
- Deliver recommendation
Milestones
18-Dec-2015 | Complete evaluation and agree use case for Stage 2 |
18-Jan-2016 | Deliver Recommendation |
25-Jan-2016 | Close |
Project RAG Status
GREEN
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days