Report for July 2021
- Report Date
- July 2021
Achievements this Period
- OCS deployment to Schools underway
Issues
- Delivery and Closure milestones to be pushed back to account for time needed to confirm rollout is working
- Work required by Desktop Services to deal with legacy tags in CSE
Next Steps
- Confirm OCS tags are being picked up and can be viewed by School Computing Officers
- Close project
Milestones
Stage | Milestone | Due Date | Complete |
---|---|---|---|
Initiate | Project Initiation | 24-Jan-2020 | Yes |
Plan | End of Planning | 05-Jun-2020 | Yes |
Analyse | OCS Configuration Review | 02-Jul-2020 | Yes |
Analyse | CSE Hardware Asset Analysis Review | 02-Jul-2020 | Yes |
Execute | Implementation Checkpoint Review Milestone | 09-Jul-2020 | Yes |
Deliver | Configuration of OCS to accept CSE data. | 16-Jul-2021 | No |
Deliver | Deployment Review | 16-Jul-2021 | No |
Deliver | Deployment of CSE data to OCS | 16-Jul-2021 | No |
Close | Closing | 23-Jul-2021 | No |
- Approved budget
- 49.0 days
- Activity this month
- 1.3 days
- Activity this year
- 16.3 days
- Activity to date
- 46.4 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 2.0 days