Report for July 2021

Report Date
July 2021

Achievements this Period

  • OCS deployment to Schools underway

Issues

  • Delivery and Closure milestones to be pushed back to account for time needed to confirm rollout is working
  • Work required by Desktop Services to deal with legacy tags in CSE

Next Steps

  • Confirm OCS tags are being picked up and can be viewed by School Computing Officers
  • Close project

Milestones

 

Stage Milestone Due Date Complete
Initiate Project Initiation 24-Jan-2020 Yes
Plan End of Planning 05-Jun-2020 Yes
Analyse OCS Configuration Review 02-Jul-2020 Yes
Analyse CSE Hardware Asset Analysis Review 02-Jul-2020 Yes
Execute Implementation Checkpoint Review Milestone 09-Jul-2020 Yes
Deliver Configuration of OCS to accept CSE data. 16-Jul-2021 No
Deliver Deployment Review 16-Jul-2021 No
Deliver Deployment of CSE data to OCS 16-Jul-2021 No
Close Closing 23-Jul-2021 No
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
Within Tolerance
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
49.0 days
Activity this month
1.3 days
Activity this year
16.3 days
Activity to date
46.4 days
Estimate to complete current year
0.0 days
Estimate to complete future years
2.0 days

Project Info

Project
Deployment of Open Computer and Software Inventory
Code
SCE017
Programme
SCE Portfolio Projects (OTHSCE)
Management Office
ISG PMO
Project Manager
Alan Donald
Project Sponsor
Victoria Dishon
Current Stage
Close
Status
Closed
Project Classification
Transform
Start Date
27-Jan-2020
Planning Date
05-Jun-2020
Delivery Date
10-Aug-2021
Close Date
17-Sep-2021
Overall Priority
Normal
Category
Discretionary

Documentation