Report for March 2021

Report Date
March 2021

Achievements this Period

  • BA completed and circulated the AS-IS.
  • BA planning worshop to support definitation of TO-BE.
  • Change to Planning Date 

Issues

  • Delay in planning completion due to lack of PM availability.

Next Steps

  • Plan work  and write Project Brief

Milestones

Date Milestone
22-Jan-2021 Project Initiation
23- Apr-2021 Planning
04-Jun-2021 Delivery
02-Jul-2021 Closure

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
80.0 days
Activity this month
4.8 days
Activity this year
12.2 days
Activity to date
12.2 days
Estimate to complete current year
23.2 days
Estimate to complete future years
0.0 days

Project Info

Project
GradeScope Evaluation
Code
SCE018
Programme
SCE Portfolio Projects (OTHSCE)
Management Office
ISG PMO
Project Manager
Muriel Mewissen
Project Sponsor
Victoria Dishon
Current Stage
Execute
Status
In Progress
Project Classification
Transform
Start Date
22-Jan-2021
Planning Date
23-Apr-2021
Delivery Date
09-Jul-2021
Close Date
16-Jul-2021
Programme Priority
1
Overall Priority
Normal
Category
Discretionary

Documentation