Closure Report

Project Summary

The ClimateXChange are considering moving their files from Datastore and other locations to SharePoint. This project carried out a requirement gathering exercise to specify and size the work required to move to a SharePoint solution.

Scope

This project carried out a requirement gathering exercise to specify, size and document the needs of CXC and identified recommendations and options for next steps along with the effort required for the work.

Out of Scope

The development, implementation and subsequent reporting of any solution.

Objectives and Deliverables

The objective of this project was a requirement gathering exercise to specify and size the work required to move to a SharePoint solution.

ID Description

Priority (MoSCoW)

Achieved? / Outcome
O1 Gather and document requirements    
O1D1 Project workshops MUST Complete
O1D2

Business Requirements Document (BRD)

MUST Complete
O1D3 Options Appraisal Document MUST Complete

Benefits

Benefit Owner Achieved? / Outcome
Understanding of various options and functionalities that SharePoint and O365 can provide to CXC to  improve their current   processes and set up. Project Sponsor Complete
Costs estimate for each option and possible add-on (permissions, workflows, integrations, migration...) Project Sponsor Complete - CXC requested a second, revised, "stripped back" estimate due to the costs involved

Analysis of Resource Usage:

Staff Usage Estimate: 10.0 days

Staff Usage Actual: 15.6 days

Explanation for Variance

Multiple delays were experienced due to the availability of the Service Management team/Technology Lead and one delay was due to the absence of the Programme Manager. This resulted in the project milestones having to be changed and submitted to Apps Review for authorisation.

The production of the Business Requirements Document (BRD) was effected by the availability of the Service Management team/Technology Lead as it required their input. Upon their reviews, the document required further work. This then resulted in additional meetings with CXC to review it.

Upon receipt and review, CXC requested a second, revised estimate that covered a more basic solution due to the costs involved, taking into account where they currently are in their funding cycle. This resulted in Service Management having to spend more time creating the new estimate as well as more meetings to discuss it with CXC.

The resource variance has already been raised to the Progamme Manager throughout the project.

Outcome

The Business Requirements Document (BRD) was produced alongside the Options Appraisal Document and both were presented to the ClimateXChange (CXC). Upon receipt and review, CXC requested a second, revised estimate that covered a more basic solution due to the costs involved, taking into account where they currently are in their funding cycle. The ClimateXChange have taken the new, revised estimate to their management for review and authorisation to proceed. Should they wish to proceed, a new project will be opened.

Key Learning Points

Ref Title Impact Theme Stage
1 Availability of Service Management/Technology Lead Was detrimental Resourcing Execute
2 Availability of Programme Manager Was detrimental Resourcing Plan
3 Separate Project and Budget for Business Analysis Was detrimental Business Analysis Analyse

Outstanding Issues

The ClimateXChange and their management are currently reviewing the revised estimate and should they choose to proceed, a new, separate project will be opened.

 

 

 

 

Project Info

Project
ClimateXChange Document Management SharePoint - Requirements
Code
SCE022
Programme
SCE Portfolio Projects (OTHSCE)
Management Office
ISG PMO
Project Manager
Jack Ross
Project Sponsor
Lee Callaghan
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
22-Jan-2024
Planning Date
26-Feb-2024
Delivery Date
05-Jun-2024
Close Date
06-Jun-2024
Programme Priority
1
Overall Priority
Normal
Category
Discretionary

Documentation

Close