Project Report for January 2024
- Report Date
- January 2024
Achievements this period
- Project initiated
- Held 2 workshops - covering big picture of CXC Team and their Project Tracker
- Flow diagrams produced
Issues
- None
Next Steps
- Complete Project Brief
- Multiple more workshops
Milestones
Stage | Milestone | Due Date | Previous Date | Complete |
---|---|---|---|---|
Initiate | Project Start Date | 22-Jan-2024 | No date available | No |
Plan | Project Brief Completion | 29-Jan-2024 | No date available | No |
Deliver | Delivery of Project Outcomes | 16-Feb-2024 | No date available | No |
Close | Target Date For Project Closure | 23-Feb-2024 | No date available | No |
- Approved budget
- 10.0 days
- Activity this month
- 3.3 days
- Activity this year
- 5.4 days
- Activity to date
- 5.4 days
- Estimate to complete current year
- 5.6 days
- Estimate to complete future years
- 0.0 days