Project Report for April 2024
- Report Date
- April 2024
Achievements this period
- Business Requirements Document (BRD), Options Appraisal Document and estimate(s) completed and provided to CXC
Issues
- Due to cost, CXC has requested a revised estimate from Service Management for the work done by the Sharepoint Team, with fewer functions etc
Next Steps
- Service Management to provide a revised estimate of work and visual mock-ups of system at request of CXC
- BRD and Options Appraisal Document to be signed off
- Project closure
Milestones
Stage | Milestone | Due Date | Previous Date | Complete |
---|---|---|---|---|
Deliver | Sign-off of BRD & Options Appraisal Document (MAJOR MILESTONE) | 26-Apr-2024 | 21-Mar-2024 | No |
Close | Target Date For Project Closure (MAJOR MILESTONE) | 30-Apr-2024 | 28-Mar-2024 | No |
- Approved budget
- 10.0 days
- Activity this month
- 3.1 days
- Activity this year
- 13.8 days
- Activity to date
- 13.8 days
- Estimate to complete current year
- 1.2 days
- Estimate to complete future years
- 0.0 days