Report for February 2017
- Report Date
- February 2017
Achievements this period
- Supported sponsor in Inaugural Lecture "Edinburgh City of Learning"
- Organise workshop for Edinburgh Datafest
- Review proposal for Informatics MSc student projects
- Review proposals for Cityscope funding
Issues
- Additional funding required for full-scale pilot
- Departure of IS developer lead risks delivery of wider Cityscope aims as technical champion role unfilled.
Next Steps
- Revise costings for new business case
- Meet with sponsor and EDINA to resolve technical leadership issues
- Confirm is unused effort cab be transferred into 17/18
- Approved budget
- 50.0 days
- Activity this month
- 2.0 days
- Activity this year
- 12.0 days
- Activity to date
- 12.0 days
- Estimate to complete current year
- 15.0 days
- Estimate to complete future years
- 20.0 days