Report for March 2017

Report Date
March 2017

Achievements this period

  •  Open Data festival Cityscope event held ( in reduced form)
  • Met with sponsor and VE for engagement re Citydeal bid
  • Input to Citydeal proposal
  • Secured agreement  from VP for engagement for 3-month support to work up Citydeal business case
  • Met with IS and EDINA resources to escalate resource issue now that development lead is leaving

Issues

  • Open Data festival hands-on event reduced to presentation due to lack of developer resources to support event 
  • Additional funding required for full-scale pilot (ongoing)
  • Departure of IS developer lead risks delivery of wider Cityscope aims as technical champion role unfilled (ongoing)

Next Steps 

  • Meet with sponsor and EDINA to progress resourcing for Cityscope
Project Status
RAG Status
Time
RED
Cost
GREEN
Scope
RED
Overall
RED
RAG Commentary
The RAG status is red as there are no IS developer resources currently assigned to Cityscope.
Change Status
Activity
Approved budget
50.0 days
Activity this month
2.0 days
Activity this year
12.0 days
Activity to date
12.0 days
Estimate to complete current year
15.0 days
Estimate to complete future years
20.0 days

Project Info

Project
Virtual Edinburgh PM Consultancy and Support
Code
SCEP02
Programme
SCE Portfolio Projects (OTHSCE)
Management Office
ISG PMO
Project Manager
Morna Findlay
Project Sponsor
Jonathan Silvertown
Current Stage
Execute
Status
Closed
Start Date
15-Jan-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
03-Aug-2018