- Report Date
- March 2017
Achievements this period
- Open Data festival Cityscope event held ( in reduced form)
- Met with sponsor and VE for engagement re Citydeal bid
- Input to Citydeal proposal
- Secured agreement from VP for engagement for 3-month support to work up Citydeal business case
- Met with IS and EDINA resources to escalate resource issue now that development lead is leaving
Issues
- Open Data festival hands-on event reduced to presentation due to lack of developer resources to support event
- Additional funding required for full-scale pilot (ongoing)
- Departure of IS developer lead risks delivery of wider Cityscope aims as technical champion role unfilled (ongoing)
Next Steps
- Meet with sponsor and EDINA to progress resourcing for Cityscope
- Approved budget
- 50.0 days
- Activity this month
- 2.0 days
- Activity this year
- 12.0 days
- Activity to date
- 12.0 days
- Estimate to complete current year
- 15.0 days
- Estimate to complete future years
- 20.0 days