Report for May 2017

Report Date
May 2017

Achievements this period

  • Cityscope input to Citydeal bid
    • First draft of Cityscope input to Citydeal business case circulated
    • Review meetings for Cityscope input to Citydeal business case arranged
    • EDINA technical resource identified to QA input to Citydeal business case
  • Meeting held with HSS collaborators re possible AHRC funding opportunities
  • Meeting to discuss use of Cityscope for student projects arranged
  • Cityscope steering group meeting for June arranged

Issues

  • Additional funding required for full-scale pilot (ongoing)
  • Departure of IS developer lead risks delivery of wider Cityscope aims as technical champion role unfilled (ongoing)
  • Scope, deadlines and strategy for Cityscope input to Citydeal business is unclear (ongoing)

Next Steps 

  • Review Cityscope input to Citydeal business case with Head of  IS
  • Complete final draft of  Cityscope input to Citydeal business case
  • Cityscope Steering Group meeting to be held
  • Meet with representative sof council and NMI re prospective AHRS funding opportunities
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
RED
Overall
RED
RAG Commentary
ISSUE: RED as the scope, strategy and deadlines for the Cityscope input to Citydeal remains unclear
Change Status
Activity
Approved budget
34.0 days
Activity this month
4.0 days
Activity this year
24.0 days
Activity to date
24.0 days
Estimate to complete current year
10.0 days
Estimate to complete future years
15.0 days

Project Info

Project
Virtual Edinburgh PM Consultancy and Support
Code
SCEP02
Programme
SCE Portfolio Projects (OTHSCE)
Management Office
ISG PMO
Project Manager
Morna Findlay
Project Sponsor
Jonathan Silvertown
Current Stage
Execute
Status
Closed
Start Date
15-Jan-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
03-Aug-2018
Category
Discretionary