- Report Date
- May 2017
Achievements this period
- Cityscope input to Citydeal bid
- First draft of Cityscope input to Citydeal business case circulated
- Review meetings for Cityscope input to Citydeal business case arranged
- EDINA technical resource identified to QA input to Citydeal business case
- Meeting held with HSS collaborators re possible AHRC funding opportunities
- Meeting to discuss use of Cityscope for student projects arranged
- Cityscope steering group meeting for June arranged
Issues
- Additional funding required for full-scale pilot (ongoing)
- Departure of IS developer lead risks delivery of wider Cityscope aims as technical champion role unfilled (ongoing)
- Scope, deadlines and strategy for Cityscope input to Citydeal business is unclear (ongoing)
Next Steps
- Review Cityscope input to Citydeal business case with Head of IS
- Complete final draft of Cityscope input to Citydeal business case
- Cityscope Steering Group meeting to be held
- Meet with representative sof council and NMI re prospective AHRS funding opportunities
- Approved budget
- 34.0 days
- Activity this month
- 4.0 days
- Activity this year
- 24.0 days
- Activity to date
- 24.0 days
- Estimate to complete current year
- 10.0 days
- Estimate to complete future years
- 15.0 days