Report for February 2025

Report Date
February 2025

 

Activity this Month: 

  • Handover and onboarding of the new PM
  • Discussions with COL Operations manager to identify risks and agree preferred Enquiries procedure, keeping enquiries within Dynamics strongly preferred.
  • Enquiry Management Systems Team and SCP Project team agreed and purchased EMS licenses for SCP Early Adopters.

Key Project Risks and Issues:

  • There is a risk that enquiries passed to users without access to the student enquiry CRM will be lost from the learner enquiry stats and the COL enquiry's team visibility. This will be tested with Group 2 EA course teams and if required labels or processes will be agreed.

Upcoming Decisions and activities:

  • Finalise decision on SCP enquiry management process, and begin onboarding other EA Schools, starting with Law and Usher.
  • Continue work with the web development project to test the web contact form
  • Completed end to end plan of detailed activities and resource requirements
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Short Courses Platform: Pre-registration enquiries and learner support
Code
SCP003
Programme
Short Courses Platform
Management Office
ISG PMO
Project Manager
Liz Dickie
Project Sponsor
Melissa Highton
Current Stage
Execute
Status
In Progress
Project Classification
Transform
Start Date
07-Apr-2023
Planning Date
09-Jun-2023
Delivery Date
25-Apr-2025
Close Date
27-Jun-2025
Overall Priority
Normal
Category
Discretionary

Documentation