Delegated Authority Schedule and Governance (DAS) - full project information

Current project status

Report Date RAG Budget Effort Completed Effort to complete
June 2020 AMBER 0.0 days 0.0 days 0.0
Content
Status
In Progress
Current Stage
Execute
Start Date
Tuesday, 20 June 2017
Delivery Date
Thursday, 30 April 2020
Project information
Project Code
SEPFTP002
Programme
Service Excellence - Finance Transformation Programme (SEPFTP)
Session
19/20
18/19
17/18
16/17
Organisational Unit
Finance Department
Project Management Office (if relevant)
Service Excellence PMO
Overall Priority
Normal