Status report for two-week period ending 28 May 2018
- Report Date
- May 2018
Achievements this period
- Reviewed governance arrangements for financial decision-making and approval
- Defined draft principles for sub-delegation of authority for financial approvals
- Arranged stakeholder meetings
Issues
None identified
Risks
None identified
Next steps
- Stakeholder meetings
- Agreement of principles
Milestones
Project changes approved | April 2018 |
Review of governance arrangements for financial decision-making and approval complete | May 2018 |
Principles for financial approval approved | July 2018 |
Principles delivered to Core Systems project | July 2018 |
RACI complete | July 2018 |
Impact assessment complete | July 2018 |
Recommendations for governance and approvals approved | Sept 2018 |
Recommendations approved by Court (if required) | Nov 2018 |
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days