Status report for two-week period ending 9 July 2018

Report Date
July 2018

 

Achievements this period

  • Final stakeholder meeting completed

Issues

Due to focus on TOM work the project has not met the 2 July 2018 deadline for delivery of the approved DAS principles to Core Systems; delivery of the agreed principles is now expected in August 2018.

The issue will be managed by briefing the FTP Programme Lead on the DAS functionality required from the Core System who will then feed requirements into the Core System dialogue sessions.

Risks

None identified

Next steps

  • Open feedback cycle
  • Agreement of principles

Milestones

Project changes approved April 2018
Review of governance arrangements for financial decision-making and approval complete May 2018
Principles for financial approval approved July 2018
Principles delivered to Core Systems project July 2018
RACI complete July 2018
Impact assessment complete July 2018
Recommendations for governance and approvals approved Sept 2018
Recommendations approved by Court (if required) Nov 2018

 

 

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Delegated Authority Schedule and Governance (DAS)
Code
SEPFTP002
Programme
Service Excellence - Finance Transformation Programme (SEPFTP)
Management Office
Service Excellence PMO
Project Manager
Susan Mulhearn
Project Sponsor
Rachael Robertson
Current Stage
Execute
Status
In Progress
Start Date
20-Jun-2017
Planning Date
n/a
Delivery Date
30-Apr-2020
Close Date
n/a
Overall Priority
Normal

Documentation

Not available.