Status report for the period ending 26 November 2018
- Report Date
- November 2018
Achievements this period
Principles agreed and delivered to Core System Project
Issues
N/A
Risks
None identified
Next steps
- Temporarily suspend project until completion of Research TOM work
Milestones
Project changes approved | April 2018 |
Review of governance arrangements for financial decision-making and approval complete | May 2018 |
Principles for financial approval approved | Nov 2018 |
Principles delivered to Core Systems project | Nov 2018 |
RACI complete | TBC |
Impact assessment complete | TBC |
Recommendations for governance and approvals approved | TBC |
Recommendations approved by Court (if required) | TBC |
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days