Fortnight ending 1st September 2017
- Report Date
- September 2017
Achievements this period
- Consultant procured;
- Finalise and gain approval of the PID;
- Identified members for the validation group;
- Benefits planning for the capturing of the baseline.
Issues
There has been no issues identified in this period.
Risks
There has been no risks identified in this period.
Next steps
- Communications developed for updating individuals about the project and current activities;
- Consultant started;
- Review work planned, agreed, commenced;
- Development of handover information.
Milestones
Milestone |
Date |
DAS review complete |
Wednesday 22th November 2017 |
Governance review complete |
Wednesday 22th November 2017 |
Recommendations update |
Wednesday 6th December 2017 |
Recommendations complete |
Monday 19th February 2018 |
Validation group approval |
Monday 19th February 2018 |
Pre launch check |
Monday 2nd April 2018 |
New DAS launch |
Monday 16th April 2018 |
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days