Maximising the University's financial resources through streamline and standardised processes and policies for Finance Specialist Services.

Current project status

Report Date RAG Budget Effort Completed Effort to complete
January 2021 AMBER 0.0 days 0.0 days 0.0

Project Info

Project
Finance Specialist Services
Code
SEPFTP015
Programme
Service Excellence - Finance Transformation Programme (SEPFTP)
Management Office
ISG PMO
Project Manager
Kerry Richardson
Project Sponsor
Chris Cope
Current Stage
Plan
Status
In Progress
Start Date
01-Jul-2019
Planning Date
08-Oct-2019
Delivery Date
n/a
Close Date
n/a
Overall Priority
Normal

Documentation

Not available.

Project Dashboard

Project journal

No entries found.

Change dashboard

Nothing to report.