Q2 2017/18

Report Date
January 2018

Some progress made around feasibility of Wind Responsive ventilation, and plans for implementation on Fume Cupboards underway. Developing a Sustainable Lab Ventilation Policy with associated guidelines, and a Sustainable Cold Storage policy with associated guidelines , the first drafts of which were taken to SLSG for discussion, and feedback gained.

Progress slower than hoped on Lab Design/Edinburgh Standard work, but stakeholders fully engaged.

Case examined for -70 campaign and discussed with SLSG - option chosen to move forward (see full report for details) is not a blanket campaign, but a guidance approach.

 

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
GREEN
RAG Commentary
Amber on time due to delays in Design guidelines, although this is outwith SRS control.
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
SLB2 Utilities, Waste and Carbon Saving
Code
SLB2
Programme
SRS - Sustainable Laboratories (SLB)
Project Manager
Andrew Arnott
Project Sponsor
Michelle Brown
Current Stage
Deliver
Status
In Progress
Start Date
01-Aug-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
31-Jul-2022
Overall Priority
Normal