Q4 2017/18

Report Date
August 2018

The Wind Responsive Ventilation project has not yet progressed. Due to the refurbishment planned at the Joseph Black building, further information is required from the Estates Committee meeting in September before progressing. 

Sustainable Lab Ventilation Policy with associated guidelines, and a Sustainable Cold Storage Facility design policy with associated cold storage guidelines have been presented to the SLSG in May and both were approved. These documents are being prepared for publication.

Cold Storage Sustainability Facilitator internship was successfully carried out with a final report having been distributed with internal and external networks. 

3 labs projects were proposed and approved for funding.

 

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
GREEN
RAG Commentary
Amber grade for 'Time' due to uncertainty of timing of works at Chemistry and the impact this may have on SCF approved and proposed projects. Costs for Wind Responsive Ventilation projects could be very substantial, but should be able to be covered by SCF and/or Estates.
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
SLB2 Utilities, Waste and Carbon Saving
Code
SLB2
Programme
SRS - Sustainable Laboratories (SLB)
Project Manager
Andrew Arnott
Project Sponsor
Michelle Brown
Current Stage
Deliver
Status
In Progress
Start Date
01-Aug-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
31-Jul-2022
Overall Priority
Normal

Documentation