Q2 2018/2019

Report Date
February 2019

The Joseph Black Building Wind Responsive Ventilation project will be carried out in phases. Initially a limited project focusing on changing fume hood controls in Lab 29 will be carried out in Q2/Q3 2018/2019.

The Sustainable Lab Ventilation and Sustainable Cold Storage Facility best practice documents have been published on the SRS website.

6 labs projects were proposed and approved for SCF funding.

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
GREEN
RAG Commentary
Amber grade for 'Time' due to uncertainty of timing of works at Chemistry and the impact this may have on SCF approved and proposed projects. Costs for Wind Responsive Ventilation projects could be very substantial, but should be able to be covered by SCF and/or Estates.
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
SLB2 Utilities, Waste and Carbon Saving
Code
SLB2
Programme
SRS - Sustainable Laboratories (SLB)
Project Manager
Andrew Arnott
Project Sponsor
Michelle Brown
Current Stage
Deliver
Status
In Progress
Start Date
01-Aug-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
31-Jul-2022
Overall Priority
Normal

Documentation

Not available.