Q4 2017/18

Report Date
August 2018

Technician Commitment requires development of an Action Plan for 2017-18 and for 2018-2020.  The 2017-18 plan has been agreed by the TSSG and is being acted upon. The 2018-2020 plan has not formally been agreed (no particular problems anticipated) due to shortage of time at TSSG meetings. High priority actions are underway but a lack of regular meetings has resulted in slower progress on some actions than expected. A meeting with the Principal has been scheduled for the 29th Aug. The Principal is still committed to attend the Technician Commitment launch event in December 2018, planning for which is well underway.

The Website and social media feeds have not been as well managed as planned due to staff annual leave over summer. Technician survey results have been collated and will be published in the form of an infographic after further input from the working group. The proposed new chair of the TSSG (Jon Kelly) is still awaiting approval and without a chair the TSSG meetings have not been organised as regularly as expected.

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
RAG Commentary
Over summer time pressures have impacted motivation from TSSG members and progress has been slower than expected. However as SRS leadership is expected to be reduced, this should not impact SRS Scope.
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
SLB4 Technical Staff CPD
Code
SLB4
Programme
SRS - Sustainable Laboratories (SLB)
Project Manager
Andrew Arnott
Project Sponsor
Michelle Brown
Current Stage
Deliver
Status
In Progress
Start Date
01-Aug-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
31-Jul-2022
Overall Priority
Normal

Documentation

Not available.