Q3 2018/2019

Report Date
May 2019

Technician Commitment requires development of an Action Plan for 2017-18 and for 2018-2020.  The 2017-18 plan has been agreed by the TSSG and is being acted upon. The 2018-2020 plan is under development. High priority actions are underway but a lack of regular meetings has resulted in slower progress on some actions than expected. 

The Technician Commitment launch event  successfully took place on the 5th December 2018.  Since then 3 Technet events have taken place at QMRI (February), the Informatics Forum (March) and KB (Engineering) (April), with SRS contributing talks at the first two events. There is positive feedback for these events and an increasing number of individuals offering to support and act as local champions.

An update report on progress against the Implementation Plan is being produced for People Committee.

Work continues to develop an up to date technicians email list. 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
SLB4 Technical Staff CPD
Code
SLB4
Programme
SRS - Sustainable Laboratories (SLB)
Project Manager
Andrew Arnott
Project Sponsor
Michelle Brown
Current Stage
Deliver
Status
In Progress
Start Date
01-Aug-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
31-Jul-2022
Overall Priority
Normal

Documentation

Not available.