Report for July 2018
- Report Date
- July 2018
Achievements in Last Period
- JIRA review and a number have been actioned and closed, or agreed to go into support
- Closure report written and distributed
Issues
- Final 2 QuickCalls JIRAs have been returned to the developer after testing by Service Management. They have now been re-developed and passed back to Service Management for re-testing and deployment. It has been difficult to get developer time to complete the work and re-work due to demand, so project closure has been delayed.
Next Steps
- JIRAs for QuickCalls deployed to LIVE
- Deployment Sign off for QuickCalls
- Project Closure agreed
Milestones
03-Aug-2018 | Closure |
- Approved budget
- 345.0 days
- Activity this month
- 8.0 days
- Activity this year
- 354.0 days
- Activity to date
- 357.0 days
- Estimate to complete current year
- 1.0 day
- Estimate to complete future years
- 0.0 days