Report for September 2018

Report Date
September 2018

Achievements in Last Period

  • QuickCalls bug for Durham applied to TEST, tested and will be put live after change freeze
  • Project Closure report amended after meeting, reviewed and signed off
  • Project closure agreed

 

Issues

  • None

 

Next Steps​

  • Project is now closed
Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
345.0 days
Activity this month
5.0 days
Activity this year
9.0 days
Activity to date
364.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days